Correction Slips Issued after the publication of the last
issue of the Journal

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 (EDITION)

Advance Correction Slip No.63 dated 27.1.2000.
(Ref. Railway Board's letter No.98/CE-II/CS/1 dated 27.11.2000).

The following para be added at end of the existing para - 275(3) of IRPWM - 1986: -

The fixing of guard rail on concrete sleepers shall be done as shown in drawing No.RDSO/T-4088 to 4097 by proper tightening of rail screws. Provision of MS flats/tie bars for tying PRC sleepers together at ends is not required.

BACK

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)


ADVANCE CORRECTION SLIP No. 64 Dated 05-01-2001
(Ref. Railway Board's letter No. 99/CE-I/LX/80dated 05.01.2001).


The para 901 of chapter IX of IRPWM - 1986 modified vide correction slip No.35 dated 19.08.99 be re-modified to read as under: -

901 General Location: As far as possible, new Level Crossings may not be located in busy station yards where heavy detention to the road traffic and other operational problems are likely to be encountered. If provision of Level Crossing is inescapable it may be located outside the outermost facing points. For Level Crossings already located within busy station yards affecting Railway operations and causing heavy detention to the road traffic, efforts should be made to replace them by Road Over/ Under Bridges as per extant rules or shift them outside the outer most facing points, especially during planning of gauge conversions, yard re-modelling and doublings and its operation from the cabin should be possible.

BACK

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)

ADVANCE CORRECTION SLIP No. 65 Dated 01-03-2001
(Ref. Railway Board's letter No. NO.99/CE-II/TK/Misc. dated. 01.03.2001).

The existing para 309 of Indian Railways Permanent Way Manual be renumbered as 309 (B).

A new para 309(A) be added to read as under:

309 (A) Project report for track renewal works : Systematic and meticulous planning for various items of execution of track works is essential for achieving quality, economy and timely completion of works. For every sanctioned track work e.g. CTR, TSR, TRR, deep screening, bridge timber renewal, etc. a detailed project report should be prepared. The report should, inter alia, cover the following aspects:

i) Details of work - Pink book detail, scope of work, locational details, cost and estimate particulars etc.
   
ii)

Existing track structure - Inventory of existing track structure including the rails, sleepers, fittings, ballast quantity/deficiency in track, type, width of formation and other details should be taken as prescribed in P.Way diagram, details of level crossings, bridges, electrical fittings, curves, height of bank/cuttings, yards, sidings, etc.

   
iii)

Classification of track materials - During inventory of the existing track structure by foot by foot survey, identification, classification and colour marking of existing track materials as second hand and scrap would be done as provided in para 320 of the IRPWM. The classification should be approved by the competent authority. Action plan for stacking/storage and disposal of the released materials should be clearly indicated. Inventory of existing track material would normally be prepared jointly by the PWI of the section and the PWI(Spl) for the renewal.

   
iv)

Proposed track structure - The proposed P.Way diagram of the affected length should be prepared in the same format as done for the existing track structure and incorporated in the project report.

   
v)

Existing/proposed gradient profile - The levels of existing track should be taken at every 20 metres and a gradient diagram prepared. Introduction of vertical curves should be critically examined and the proposed profile of track shown in red line indicating the proposed grades. Lowering of track should be avoided. Precise lift of track at girder bridges should be worked out and a separate scheme developed for lifting of girders on each of the affected bridges. Similarly, the magnitude of lifting at level crossing should be worked out and indicated in the report. Care should be exercised to keep the road surface in one level on level crossings spanning to across multiple tracks. This may require regrading of adjacent lines too.

   
vi)

Realignment of curves - All curves should be measured afresh and slews worked out for realignment wherever necessary, keeping in the obligatory points in view.

   
vii)

Method of execution -The work should be executed "bottom upwards" i.e. sequence of execution of works will be in the following order-

  Formation > Ballast > Sleepers > Rails.
   
viii) Formation:
a)

Repair and widening of cess: The project report should indicate the requirement of and plan for widening of formation in both banks and cuttings wherever necessary. Provision of proper drains in cuttings should also be planned.

   
b)

Formation treatment: Areas needing formation rehabilitation should be identified and a study for possible solutions and method of execution of the rehabilitation scheme should form part of the project report.

   
ix)

Ballast - The requirement indicating bifurcation of cess supply and depot supply and the source and means of each should be spelt out clearly. Mode of providing ballast cushion i.e. deep screening or raising should be identified along with sketches of cross sections present and proposed. Sleeper renewal would normally not be started unless adequate arrangements for supply of ballast have been made.

   
x)

Transportation of P.Way materials - The mode of transportation for various track components and unloading of rails and sleepers in particular, at the work sites should be indicated in the project report.

   
xi)

Welding - The complete details of welding requirements, the arrangements need to be made for its execution whether departmentally or through contract should be clearly indicated in the report.

   
xii)

Renewal of turnouts, bridge timbers, etc. - The project report should cover the complete details of turnouts, bridge timbers, level crossings, etc. where renewal is to be carried out. Whether turnouts are to be laid manually or by mechanized means, should be clearly brought out indicating the arrangements made. The report should also include the mode and agency for overhauling and relaying and making up of road surface at the level crossings.

   
xiii)

Use of machines -The requirement of machines for renewal (if mechanized renewal is planned) deep screening (if mechanized deep screening is planned) and tamping/stabilizing and the duration for which the machines are required should be indicated. The machines that would be deployed should be identified and staff nominated. The planning for repair of machines at the works site, supply of fuel and other consumables should be planned. The requirement of additional lines in the existing yards for making base depot and arrangements made for the same should be indicated in the report

   
xiv)

Contracts - The contracts that are required to be entered into for various activities of works and the activities, which are to be done departmentally, should be spelt out. The planning for deployment of staff/supervisors for execution at various activities should be indicated.

   
xv)

Material Planning - The material requirement should indicate the materials to be arranged by the headquarters and by the Divisions. Against each material, the proper nomenclature and drawing number should be indicated. Rails, nos. and sizes (including lead rails, check rails etc.), sleepers (including specials), rail and sleeper fastenings, switches and crossings, level crossing and bridge sleepers and fittings, etc. should be fully covered. The consignee particulars and the destination, the mode of transport should also be indicated.

   
xvi)

Manpower Planning - The requirement of manpower including the officers, supervisors, artisan and other staff should be worked out with minute details. The arrangements made for camping of these officials and mobilization should be reflected in the report.

   
xvii)

LWR/CWR plans - For welding of rails into LWR/CWR, the LWR plan should be got approved by the competent authority well in advance. Such plan should form part of the project reports.

   
xviii)

Requirement of speed restrictions, traffic blocks and other material train - Planning for execution of track renewal works should be such that the time loss on account of speed restriction is minimal and is within the permissible limits. The report should indicate requirement of speed restrictions and traffic blocks together with durations. The corridor for blocks is required to be planned in consultation with the Operating Department and accordingly reflected in the report after obtaining the approval of DRM. Arrangements made for various types of wagons for transportation of ballast, sleepers, etc. together with requirement of locomotives should be indicated in the report in consultation with Sr.DOM and with the approval of DRM.

   
xix)

Monitoring mechanism - The list of all activities involved and the time estimation for each activity should be worked out. These activities should be sequenced and co-related in logical manner and network diagram prepared using CPM method. The critical activities should thus be identified. These should form part of the project report.

   
xx)

The detailed project report covering the various points as mentioned above should be prepared as soon as the approval of Board to include the works in FWP is conveyed to the railways. These reports should be submitted to headquarters for scrutiny and approval.

  BACK
 

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)

Advance Correction Slip No. 66 Dated 30.3.2001
(Ref. Railway Board's letter No.2000/CE-II/PRA/1 dated 30.03.2001)

A new Para 914 (b) (v) be added to chapter IX of IRPWM to read as under:-


Check rails of level crossings are required to be removed for tamping operation, overhauling of level crossings, destressing of LWR or track renewal etc. Check rails should be re-fixed as quickly as possible and preferably before leaving site. Should a situation arise where check rails cannot be re-fixed for any reason and trains have to be passed, a speed restriction of 30 kmph should be imposed besides ensuring that road traffic is diverted till the check rails are put in place.

BACK
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)


ADVANCE CORRECTION SLIP No. 67 Dated 24.4.2001
(Ref. Railway Board's letter no. 98/CE-II/TK/Misc./3 dated 24.04.2001)

 
The para 1408 of Chapter XIV to IRPWM be deleted and substituted with a new para 1408 as under :-
1408 Maintenance of concrete sleeper track
 
(1)  General
(a) Concrete sleeper track should be maintained by heavy on-duty track tampers.
 
(b)

An annual machine deployment programme shall be drawn by zonal railway and be circulated to the divisions before the beginning of the year.

 
(c)

For spot attention/slack picking, multi purpose tampers and off-track tampers shall be used. Where off-track tampers are not available, as an interim measure, the packing may be done with the help of crow bar/beater duly taking care that the concrete sleepers are not damaged.

 
(d)

Pre-tamping, during tamping and post-tamping attentions should be given to track as indicated in para 226. (For further details, Chapter 3 of Indian Railways Track Machine Manual may be referred to).

 
(2)  Annual Systematic Attention on PRC track
In addition to machine tamping, the gangs will carry out annual systematic attention to track from one end of gang beat to the other during work season. This will include -
(a) Examination of rails, sleepers and fastenings including measurement of toe load of ERCs.
 
(b) Inspection of and attention to insulated joints, switch expansion joints etc.
 
(c) Packing of approaches of bridges, level crossings, breathing lengths of LWRs and bad formation areas etc.
(d) Shallow screening of track..
 
(e) Through packing of tracks not maintained by machine, e.g. tracks not on PSC sleepers including all running lines of the yards and points and crossings in such running lines.
(f) Minor repairs to cess and bank.
 
(g) Boxing and dressing of ballast.
 
(h) Replacement of damage/missing rubber pads, liners and ERCs.
 
  (3) Annual Programme of maintenance of PRC track
 
The annual maintenance programme for machine maintained concrete sleeper track would be as under: -
Period Work
(a) Post monsoon attention:
(For six - seven months after end of monsoon)

Immediately after end of monsoon, attend to run down stretches in the entire gang length. Thereafter, the following schedule of work shall be followed :-

(i) Picking of slacks 1-2 days in a week.
(ii) Remaining days shall be allotted to:
(a) Annual systematic attention.
(b) Overhauling of level crossings.
(c) Destressing of LWRs.
(d) Spot renewals of rails, sleepers etc.
(e) De-weeding.
(f) Cold weather patrolling, etc.
(b) Pre-monsoon attention:
(For two months prior to onset of monsoon)
(i) Picking of slacks 1-2 days in a week.
(ii) Remaining days shall be allotted to:
(a) Cleaning and repairs to side and catch water drains and cleaning of water ways.
(b) Attention to yard drainage.
   
(c) Spot renewals of rails, sleepers etc.
   
(d) Shallow screening of specified lengths.
   
(e) Hot weather patrolling.
 
(c) Attention during monsoon:
(For 3-4 months)
(a) Picking of slacks as required
   
(b) Normal track maintenance of yard lines.
   
(c) Cleaning, removal of loose boulders from cuttings and tunnels to ensure free flow of water.
   
(d) Monsoon patrolling
   
(e) Maintenance of side and catch water drains.
   
(f) Repairs to cess and bank.
   
Note:  
   
(i) For maintenance schedule on LWR track, special instructions in the LWR Manual should, in addition, be followed.
 
(ii) Spot renewal of rails and sleepers shall be done as per requirement any time of the year.
   
(iii) Destressing of LWRs shall be done as per requirement and schedule to be prepared by the PWI, as per provisions of LWR Manual.
 
(iv) Main tamping, pre and post tamping works shall be done as per schedule of working of the tamper. PWI and AEN should be advised atlease one month in advance of the programme of the machine to enable them to complete pre-tamping operations.
   
(v) Lubrication of ERC's shall be done by Keyman throughout the year as per para 1411(5) (b) of the Manual.
(vi) Oiling and greasing and visual inspection of fish plated joints shall be done as per para 241 of the Manual.
BACK
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)

ADVANCE CORRECTION SLIP No. 68 Dated 25.4.2001

The Annexure 2/3 to para 206 of IRPWM be replaced with the Annexure 2/3 enclosed.

The new paras as indicated below be added to the existing para 206 of IRPWM - 1986:-
   
(4)

Maintenance attention given to the signalled loop lines and turnouts should be recorded on the chart.

   
(5)

Whenever the gang equipments are checked by PWIs, the same should be recorded in gang chart against the date on which such inspection is done. Inspecting officials should initial against the date on the chart and also make suitable entries in gang diary.

   
(6)

Six months after the end of each year, the gang charts will be collected by the PWIs and maintained as record. Thus, for the overlapping period of six months, the gang will have two gang charts with them. A six months record will therefore always be available with the gang for reference. Normally, this record should be kept for atleast five years. When a particular kilometre or section is under special observation, the record may be maintained for a longer period at the discretion of P.Way officials.

BACK

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)

ADVANCE CORRECTION SLIP No. 69 Dated 23.05.2001

A new para no. 826 be added to Chapter VIII of the IRPWM, 1986 to read as under:

826 Safe working of contractors - A large number of men and machinery are deployed by the contractors for track renewals, gauge conversions, doublings, bridge rebuilding etc. It is therefore essential that adequate safety measures are taken for safety of the trains as well as the work force. The following measures should invariably be adopted:

i) The contractor shall not start any work without the presence of railway supervisor at site.
   
ii)

Wherever the road vehicles and/or machinery are required to work in the close vicinity of railway line, the work shall be so carried out that there is no infringement to the railway's schedule of dimensions. For this purpose the area where road vehicles and/or machinery are required to ply, shall be demarcated and acknowledged by the contractor. Special care shall be taken for turning/reversal of road vehicles/machinery without infringing the running track. Barricading shall be provided wherever justified and feasible as per site conditions.

   
iii)

The look out and whistle caution orders shall be issued to the trains and speed restrictions imposed where considered necessary. Suitable flagmen/detonators shall be provided where necessary for protection of trains.

   
iv)

The supervisor/workmen should be counseled about safety measures. A competency certificate to the contractor's supervisor as per proforma annexed shall be issued by AEN which will be valid only for the work for which it has been issued.

   
v)

The unloaded ballast/rails/sleepers/other P.Way materials after unloading along track should be kept clear off moving dimensions and stacked as per the specified heights and distance from the running track.

   
vi) Supplementary site specific instructions, wherever considered necessary, shall be issued by the Engineer in Charge.
 
Annexure to para -826

COMPETENCY CERTIFICATE

 

Certified that shri _____________________P.way supervisor of M/s. _________________________ has been examined regarding P.Way working on ____________________work. His knowledge has been found satisfactory and he is capable of supervising the work safely.

BACK
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
  ADVANCE CORRECTION SLIP No. 70 Dated 24.05.2001
(Ref. Railway Board's letter No. 98/CE-II/CS/2 dated 24.05.2001)
  Note (1) to para 204 be modified to read as under:
 

Scattered renewals, creep adjustments and earth work repairs should be done as necessary.

Para 245 (e) be modified to read as under:

(e)

While doing casual/scattered renewals, priority should be given in replacing unserviceable joint sleepers and unserviceable consecutive sleepers. Through sleeper renewals should be carried out in continuous stretches and released sleepers after reconditioning should be used for scattered renewals. New sleepers should not be used in sidings. If the percentage of unserviceable sleepers becomes high, speed restrictions may have to be imposed.

   
  The following be added to para 301(1):
   
(8) Scattered Renewal
   
  The existing sub para 301(3) be renumbered as 301(4) and modified to read as under:
   
(4)

Casual Renewal: In this case, unserviceable rails, sleepers and fastenings are replaced by identical sections of serviceable and nearly the same vintage or new track components. These are carried out in isolated locations of continuous but small stretches. Such renewals are not a part of normal maintenance operations and cannot be covered under scattered renewals.

A new para 301(3) be added to read as under:
   
(3)

Scattered Renewal: In this case, unserviceable rails, sleepers and fastenings are replaced by identical sections of serviceable and nearly the same vintage track components. These are carried out in isolated locations and not more than 10 rails and / or 250 sleepers in a gang beat in a year. Such renewals are a part of normal maintenance operations.

Note (I) Annexure - DTM/1 be modified to read as under:
 
Scattered renewals, creep adjustments and earth work repairs should be done as necessary.

The following line be added at end of the existing para- 252 (2) of IRPWM - 1986:-

Such an inspection on the important girder bridges and their approaches should be done twice a year.

BACK

INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (REPRINTED 1999)
ADVANCE CORRECTION SLIP No. 71Dated 17.07.2001
 
The existing para - 283(C) of Indian Railways Permanent Way Manual be replaced with the following :-

(C) No part of a tree shall be nearer than 4 metres from the nearest live conductor.Any tree or branches likely to fall on live conductors should be cut or trimmed periodically to maintain this clearance.Cutting or trimming should be done by authorised O.H.E staff .

BACK
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
ADVANCE CORRECTION SLIP No. 72 Dated 07.08.2001
The existing para - 1411 (5) (b) of Indian Railways Permanent Way Manual be replaced to read as under :-
 

(b) In Service Maintenance : Lubrication of ERCs in track should normally be carried out be keyman in a systematic manner from one end to other at the rate of 20 sleepers (80 ERC) per day. This work should not be carried out during extreme of summer and heavy rainfall. Grease graphite to the specification IS-408-1981 Gr. O should be used for this purpose. At a time, keyman should not remove ERCs on more than one sleeper. If for any reason mass lubrication of ERCs is taken up then between any two sleepers taken up for lubrication of ERCs at the same time, at least 15 sleepers shall be kept intact. The ERCs should be cleaned by wier brush and emery paper. The eye of the insert shall also be cleaned by suitable brush. After cleaning, grease graphite shall be applied to the inside surface of eye of insert and leg of ERC. Inside/Outside ERCs should be interchanged and fixed again. The lubrication of ERCs and inserts at the time of initial laying should preferably be done in base depot and thereafter should be done once in a year in corrosion prone areas and platform lines and once in two years in other areas.

 BACK
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
ADVANCE CORRECTION SLIP No. 73 Dated 02.11.2001
The existing para - 170 (6) of Indian Railways Permanent Way Manual may be modified to read as under :-
(6)  Where the beat of a Keyman consists of PRC sleepers, apart from his round of the beat, the keyman should also carry out in a systematic manner from one end greasing of the ERC and eyes of inserts at the rate of 20 sleepers per day. Greasing shall be done as per the procedures laid down in para 1411 (5) (b) of IRPWM.
 BACK
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
ADVANCE CORRECTION SLIP No. 74 Dated 26.11.2001
The existing para - 277 of Indian Railways Permanent Way Manual be replaced to read as under :-
(a)

For all Bridges :

   
(1) On the bridge approaches, sleepers with arrangement for fixing guard rails should be provided for provision of guard rails as per para 275 above.
   
(2) Full complement of track fittings at bridge approaches up to 100 meters should be provided to maintain required track geometry and effort should be made to immediately recoup deficiency noticed, if any.
   
(3) Rail level of track in approaches of bridges should be maintained, as per provision of IRPWM - 1986 under respective para and dips in rail level immediately after abutments should be avoided. The alignment and super elevation in case of curved track should also be maintained as per provisions of IRPWM - 1986 under respective para.
   
(4)

Rail joints should be avoided within three meters of a bridge abutment.

(5) In case of LWR track, full ballast section as specified in LWR Manual should be provided up to 10 meters from the abutment.
   
(6)

Switch expansion joints should be provided at the bridge approaches in LWR/CWR track as per provisions of LWR manual.

(b) For important and major bridges :-
In addition to para (a) above, following should also be provided.

 

(1) In case of CST-9 or wooden sleeper track, concrete/steel trough sleepers with elastic fastenings should be provided up to 100m/upto full breathing length wherever LWR is provided in approach of bridge.

 

(2) On the bridge approaches, for a length of about 100 meters, width of cess should be 90cm. clear of full ballast section to maintain ballast profile. For maintaining ballast section, suitable ballast retaining arrangement should also be provided.
   BACK
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
  ADVANCE CORRECTION SLIP No. 75 Dated 05.03.2002
  The first line of para 913 (a) and (b) of IRPWM -1986 together with Annexure - 9/3 (3) be replaced with the following :
   
  913 (a)    On double line, if both the lines are obstructed during the day, he shall plant a red banner flag at a distance of 5 metres from the end of the check rails on the line on which a train in expected to arrive first, then plant another red banner flag on the other side at the site of obstruction.
   
  913 (b)    On single line, if  the line is obstructed during the day, he shall plant a red banner flag at a distance of 5 metres from the end of the check rails, towards the direction from which a train in expected to arrive first, then plant another banner flag towards the opposite direction at the site of obstruction.
   
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
  ADVANCE CORRECTION SLIP No. 76 Dated 16.05.2002
  The existing para 410 (3) of the Railways permanent way manual may be modified to read as under :
   
  (3) Speed over interlocked turn-outs - (a) Speed in excess of 15 kmph maybe be permitted for straights of interlocked turnouts only under approved special instructions in terms GR .4.10/1976
   
  (b) In the case of 1 in 8-1/2, 1 in 12 and flatter turnouts provided with curved switched , higher speeds as permitted under approved special instructions may be allowed on the turnout side, provided the turn-in curve is of standard suitable for such higher speeds. Extra shoulder width of ballast of 150 mm should be provided on the outside of such turn-in curves. When these conditions are satisfied, the speeds indicated below may be permitted on turnouts provided with curved switches. While permitting speed beyond 15 kmph, provisions of para 410(4) may also be kept in view .
   
 
S.No. Type of Turnout (B.G) Permissible Speed
1. 1:8:5 curved switch 52/60 kg. on PSC sleepers 15 kmph
2. 1:8:5 symmetrical split with curved switch 52/60 kg. on PSC sleepers 30 kmph
3. 1:12 curved switch 52/60 kg. on PSC sleepers 30 kmph
   
  (c) The permissible speed on turn-outs taking off in the inside of the curve should be determined by taking into considerations the resultant radius of the lead curve which will be sharper than the lead curve for the turn outs taking off from the straight. 1 in 8-1/2 turns-outs should not be laid on inside of curves.
   
  A new para 410 (4) be added to read as under :-
  410 (4) Upgradation of speeds on turn -outs should cover a number of contiguous stations at a time. Before upgrading the speeds on the turn-out beyond 15 km/h , the track structure of loop lines be strengthened as prescribed.
  BACK
   
  INDIAN RAILWAYS PERMANENT WAY MANUAL
  LIST OF ADVANCED CORRECTION SLIPS ISSUED SINCE OCTOBER 2001 ISSUE OF THIS JOURNAL
  The following correction slip have been issued since the last issue (October 2001) of the Journal.
   
 
ACS No. Para (s) affected File No. Date of AC slip Brief subject.
77 248 & 322 No.Track/21/93/0503/7 12.8.2002 Track structure for different categories of track.
77 1408 No.98/Track-III/TK/17/Vol.II 9.9.2002 Picking up of slacks
   
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
  Advance Correction Slip No. 77 Dated 12.8.2002
(Ref. Railway Board’s letter No. Track/21/93/0503/7 dated 12.08.2002)
  Sub: Advance Correction Slip No.77 to the Indian Railways Permanent Way Manual – 1986.
   
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in the enclosed Advance Correction Slip No.77 dated 12.8.2002, to relevant para of the IRPWM, be made.
  Receipt of this letter may please be acknowledged.
   
  The para 248(2) (a) be replaced with the following :
   
  (a) Broad Gauge – The following minimum rail sections are recommended based on the speeds obtainable and the traffic conditions :
   
 
ROUTES
Traffic density in GMT A B C D. Spl D E.Spl E
More than 20 60 kg 60 kg 60 kg 60 kg 60 kg 60 kg 60 kg
10-20 60 kg 60 kg 60 kg 60 kg 52/90 60kg 52/90
5-10 60 kg 52/90 52/90 52/90 52/90 52/90 52/90
Under 5 52/90 52/90 52/90 52/90 or 60kg (SH) 52/90 or 60kg (SH) 52/90 or 60kg (SH) 52/90 or 60kg (SH)
Loop Line 52 kg IRS T –12 second quality rails or 52 kg (SH)
Pvt Sidings For sidings with operating speed more than 80 kmph and upto 100 kmph Track structure specified for D route.
For sidings with operating speed more than 50 kmph and upto 80 kmph Track structure specified for E route.
Where BOX’N or 22.1 tonne axle wagon ply or operating speeds on sidings exceed 30 and are going upto 50 kmph 52 kg IRS T-12 second quality rails or 52 kg (SH)
For other sidings with operating speed upto 30 kmph. 52 kg IRS –T-12 third quality rails also called ‘Industrial use rails’ or 52 kg (SH).
  Note : 52/90 represents 52 kg /90 UTS rail section.
  (i) Existing 90 R rails may be allowed to remain for speeds not exceeding 110 kmph.
   
  (ii) On routes identified for running of 22.1 Tonne axle load wagons, 60-kg rails shall be used on all routes.
   
  (iii) Head hardened rails should be used on (a) Local lines where dedicated EMU stock is running. (b) Ghat section with gradients steeper than 1 in 150 and/or curves sharper than 2 degree, (c) Locations where due to grades, curves, traffic density and type of stock, the rate of wear of rails is such as to necessitate rail renewal, on wear considerations, at a frequency of 10 years or so. (d) Routes where predominantly captive rolling stock is moving in close circuit movement, particularly with heavy mineral traffic. (e) The Illf rails should be laid on continuous and long stretches.
   
 

(iv) *Second hand 52 kg rails may be used on case-to-case basis, with the prior approval of Railway Board, depending upon quality of released rails available.

The existing para. - 322 of Indian Railways Permanent Way Manual be replaced to read as under:-

   
  322. Identification of different qualities or rails in the Field -
   
  (1) First Quality Rails (T -12) - Indian Railways specification IRS - T -12/96 gives the detailed specification of Flat Bottom Rails 60 kg. and 52 kg. of grade 880 MFa, 1000 MFa and 1080 MFa. 52 kg./m and 60 kg./m rails shall be classified as Class' A' and Class 'B' rails based on tolerance in End Straightness. The rails shall have rolled on it, the rail section, the Grade of steel, identification marks of the manufacturer, month and last two digits of the year of the manufacture, process of steel making and direction of rolling of rail.
   
  (2) Second Quality Rails - These are rails with relaxation in sectional tolerance as provided in Amendment to IRS- T -12/96 but other wise conforming to T-12/96 in all other respects. The identification of such rails will be one hole of 6 mm ilia, champhered at both ends, drilled at the center length of the rail and at the middle of the web. These rails shall be used only on loop lines/sidings with speed restriction of 50 kmph. These rails shall be painted with orange colour on both sides of the web for a distance of 1 metre from each end, for easy identification.
   
  (3) Third Quality Rails - In addition to above two qualities, third quality rails supplied by Steel Plants are arising, particularly during the inspection of rails while producing first quality rails as per IRS- T -12 specification. There is no deviation in chemical composition or mechanical property in 'Industrial Use' rails from that of IRS-T-12. The deviations exist only in tolerance in surface defects, dimensions and straightness. These can be used in industrial sidings where speeds are limited to 30 km p.h in B.G. and 2S km.p.h in M.G.
   
  The identification of such rails will be one hole of 12m dia., champhered at both ends, drilled at the center length of the rail and at the middle of the web. A marking “I.U.” in 18 mm, size shall be stamped on both end faces of rail. The third quality rail shall be painted with white paint on end face of the flange and on both sides of flange for a distance of 500 mm, from each end for identification.
  BACK
   
  Advance Correction Slip No. 78 Dated 9.9.2002
(Ref. Railway Board’s letter No.98/Track-III/TK/17 Vol.II dated 9.9.2002)
   
  Sub: Advance Correction Slip No.78 to the Indian Railways Permanent Way Manual – 1986.
   
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in the enclosed Advance Correction Slip No.78 dated 9.9.2002, to relevant para of the IRPWM, be made.
  Receipt of this letter may please be acknowledged.
   
  Correction Slip No.78 dated 9.9.2002
   
  The para 1408(1) (c ) of the Advance Correction Slip No.67 dated 24.4.2001 of Indian Railway Permanent Way Manual – 1986, be substituted as under: -

1408(1) (c ) – For spot attention / slack picking, multi-purpose Tampers and Off-track Tampers shall be used as a regular measure on Concrete Sleepers Track, in the following areas of application:

i) Picking up slacks in isolated stretches.
ii) Points and Crossings areas.
iii) Approaches to bridges and level crossings.
iv) Buffer rail joints /switch expansion joints in LWR section.
v) Block insulated joints /glued joints in track circuited stretches.

For off-track tampers, the working instructins, issued by Railway Board/RDSO as amended from time to time, should be followed.

As an interim measure, where off-track tampers are not available, the packing may be done with the help of Crow bar/Beater, duly taking care that the concrete sleepers are not damaged.

  BACK
   
  INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
  Advance Correction Slip No. 79 Dated 10.10.2002
(Ref. Railway Board’s letter No.97/CE-II/TK/8 dated 10.10.2002)
   
  Sub: Advance Correction Slip No. 79 to the Indian Railways Permanent Way Manual - 1986 para-283.
   
  Ministry of Railways (Railway Board) have decided that correction/addition in the enclosed Advance Correction Slip No. 79 dated 10.10.2002 in supersession of Advance Correction Slip No.71 dated 17.7.2001 Para- 283(2) (c) of IRPWM -1986 be replaced.
   
  Correction Slip No.79 dated 10.10.2002
   
  The following may be replaced in supersession of Advance Correction Slip No.71
dated 17.7.2.002 Para 283 (2) (c) of IRPWM:. 1986 to read as under:-
   
  (c) "No part of the tree shall be nearer than 4 mts from the nearest live conductor. Any tree or branches likely to fall on the live conductor should be cut or trimmed periodically to maintain the safety clearances. The responsibility for wholesale cutting of the trees, i.e. cutting of tree trunks, will rest with the Engineering Department. In the electrified territories, however, the cutting of the trees shall be done by the Engineering, Department in the presence of authorized TrD staff to ensure safety and satisfactory completion of the work. The day-to-day trimming of the tree branches, wherever required, to maintain the 4 m safety clearances from OHE shall be done by the authorized TrD staff and Supervisors.

In case of dispute, the decision whether to cut or trim a tree, shall be taken through a joint inspection of Engineering and Electrical officials.

The modalities to be adopted for cutting/trimming of the trees i.e. contractually or departmentally, may be decided by the respective departments based on local conditions. Accountal and disposal of trees cut wholesale will be done by the, Engg. Deptt. while the disposal of the trimmed tree branches will be the responsibility of the TrD Department. The expenditure for cutting/trimming of trees to maintain safe clearance for OHE, shall be debited to revenue grant of' TrD Department."
  BACK

   
  Advance Correction Slip No. 80 Dated 2.12.2002
(Ref. Railway Board’s letter No.98/CE-II/CS/2 dated 2.12.2002)
   
  Sub: Advance Correction Slip No, 80 to the Indian Railways Permanent Way Manual - 1986 para-264.
   
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in enclosed Advance Correction Slip No, 80 dated 02.12.2002, to relevant para of the IRPWM, be made.
   
  Correction Slip No.80 dated 2.12.2002
   
  New para may be inserted as 264 (4) and 264(5) of the IRPWM – 1986 as mentioned below:

Para 264 (4) – In new line construction, ballast requirements will be assessed as
per the profile (to be adopted) given in para 263 (I).

Para 264 (5) – The quantities assessed vide sub-para in (2), (3) and (4) above will be the net quantities of ballast required, to recoup the deficiencies or to provide required profile/section. The above net quantities may be enhanced suitably (say 8%) to arrive at gross quantities of ballast for the purpose of procurement action in case measurements are proposed to be taken in stacks or in wagons at originating station.

  BACK

   
  Advance Correction Slip No. 81 Dated 3.12.2002
(Ref. Railway Board’s letter No.2002/CE-II/PRA/7 dated 3.12.2002)
   
  Sub: Advance Correction Slip No. 81 to the Indian Railways Permanent Way Manual -1986 para-914.
   
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in the enclosed Advance Correction Slip No. 81 dated 03.12.2002, to relevant para of the IRPWM, be made.
   
  Correction Slip No.81 Dated 03.12.2002:
   
 

The existing Para 914 (b) (v) of Indian Railways Permanent Way Manual be modified to read as under:


(v) - Check rails of level crossings are required to be removed for tamping" operations, overhauling of level crossings, distressing of LWR or track renewals etc. Check rails should be refixed as quickly as possible and preferably before leaving site.

Should a situation arise where check rails cannot be refixed for any reason and trains have to be passed, a speed restriction of 30 kmph should be imposed besides ensuring that road traffic is diverted till the check rails are, put in place. In case such diversion is not possible, temporary arrangements should be made for passage of road traffic till the check rails are put in place. However, in both these cases, the check rails should necessarily be provided latest by close of next day. In such cases, a stationary watchman shall be posted to ensure safety.

  BACK

 

Advanced Correction Slip No.82 Dated 02..2003:
(Ref. Railway Board’s letter No. 98/CE-II/TK/2 Pt. dated 2.2003)

 



  Sub: Advance Correction Slip No. 82 to the Indian Railways Permanent Way Manual -1986 para–1122(4).
 
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in the enclosed Advance Correction Slip No. 82 dated .2.2003, to relevant para of the IRPWM, be made.
 
Correction Slip No.82 Dated 02..2003:

 
  The existing para 1122 (4) (iii) of Indian Railways Permanent Way Manual be modified to read as under:
 
 
The rail dolley shall be protected by a flagman at a distance of 1200 metre on Broad Gauge and 800 metre on MG/NG from the rail dolley, on a double line in the direction from which trains may approach, and by two flagmen one on either direction on single line. The flagmen shall also carry three detonators for use in any emergency.
  BACK



 
Advance Correction Slip No. 83 Dated 25.02.2003
(Ref. Railway Board’s letter No. 91/Track-III/TM/26 Vol.III dated 25.2..2003)

 
  Sub: Advance Correction Slip No. 83 to the Indian Railways Permanent Way Manual -1986 para–606.
 
  Ministry of Railways (Railway Board) have decided that correction/addition as indicated in the enclosed Advance Correction Slip No. 83 dated 25.2.2003, to relevant para of the IRPWM, be made.
 
  ADVANCE CORRECTION SLIP No. 83 Dated 25.2.2003
 
  The existing para 606 of Indian Railways Permanent Way Manual be modified to read as under:
 
  606. Frequency of Track Recording - Track geometry monitoring of Metre Gauge routes is not to be done by track recording car. The Broad Gauge routes should be monitored by TRC as pe