| (a) |
For
all Bridges : |
| |
|
| (1) |
On the bridge approaches, sleepers with arrangement
for fixing guard rails should be provided for provision of guard rails
as per para 275 above. |
| |
|
| (2) |
Full complement of track fittings
at bridge approaches up to 100 meters should be provided to maintain
required track geometry and effort should be made to immediately recoup
deficiency noticed, if any. |
| |
|
| (3) |
Rail level of track in approaches of bridges should
be maintained, as per provision of IRPWM - 1986 under respective para
and dips in rail level immediately after abutments should be avoided.
The alignment and super elevation in case of curved track should also
be maintained as per provisions of IRPWM - 1986 under respective para. |
| |
|
| (4) |
Rail
joints should be avoided within three meters of a bridge abutment. |
|
|
| (5) |
In case of LWR track, full
ballast section as specified in LWR Manual should be provided up to
10 meters from the abutment. |
| |
|
| (6) |
Switch
expansion joints should be provided at the bridge approaches in
LWR/CWR track as per provisions of LWR manual. |
|
|
| (b) |
For
important and major bridges :- |
|
In addition
to para (a) above, following should also be provided. |
|
|
| (1) |
In case of CST-9
or wooden sleeper track, concrete/steel trough sleepers with elastic
fastenings should be provided up to 100m/upto full breathing length
wherever LWR is provided in approach of bridge. |
|
|
| (2) |
On the bridge approaches,
for a length of about 100 meters, width of cess should be 90cm. clear
of full ballast section to maintain ballast profile. For maintaining
ballast section, suitable ballast retaining arrangement should also
be provided. |
| |
BACK |
|
 |
| |
INDIAN
RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION) |
| |
ADVANCE
CORRECTION SLIP No. 75 Dated 05.03.2002 |
| |
The first
line of para 913 (a) and (b) of IRPWM -1986 together with Annexure
- 9/3 (3) be replaced with the following : |
| |
|
| |
913 (a)
On double line, if both the lines are obstructed
during the day, he shall plant a red banner flag at a distance of
5 metres from the end of the check rails on the line on which a train
in expected to arrive first, then plant another red banner flag on
the other side at the site of obstruction. |
| |
|
| |
913 (b)
On single line, if the line is obstructed
during the day, he shall plant a red banner flag at a distance of
5 metres from the end of the check rails, towards the direction from
which a train in expected to arrive first, then plant another banner
flag towards the opposite direction at the site of obstruction. |
| |
|
| |
INDIAN
RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION) |
| |
ADVANCE
CORRECTION SLIP No. 76 Dated 16.05.2002 |
| |
The existing
para 410 (3) of the Railways permanent way manual may be modified
to read as under : |
| |
|
| |
(3) Speed over
interlocked turn-outs - (a) Speed in excess of 15 kmph maybe be permitted
for straights of interlocked turnouts only under approved special
instructions in terms GR .4.10/1976 |
| |
|
| |
(b) In the
case of 1 in 8-1/2, 1 in 12 and flatter turnouts provided with curved
switched , higher speeds as permitted under approved special instructions
may be allowed on the turnout side, provided the turn-in curve is
of standard suitable for such higher speeds. Extra shoulder width
of ballast of 150 mm should be provided on the outside of such turn-in
curves. When these conditions are satisfied, the speeds indicated
below may be permitted on turnouts provided with curved switches.
While permitting speed beyond 15 kmph, provisions of para 410(4) may
also be kept in view . |
| |
|
| |
| S.No. |
Type of Turnout (B.G) |
Permissible Speed |
| 1. |
1:8:5 curved switch 52/60 kg. on PSC sleepers |
15 kmph |
| 2. |
1:8:5 symmetrical split with curved switch 52/60
kg. on PSC sleepers |
30 kmph |
| 3.
|
1:12 curved switch 52/60 kg. on PSC
sleepers |
30
kmph |
|
| |
|
| |
(c) The permissible
speed on turn-outs taking off in the inside of the curve should be
determined by taking into considerations the resultant radius of the
lead curve which will be sharper than the lead curve for the turn
outs taking off from the straight. 1 in 8-1/2 turns-outs should not
be laid on inside of curves. |
| |
|
| |
A new
para 410 (4) be added to read as under :- |
| |
410 (4) Upgradation
of speeds on turn -outs should cover a number of contiguous stations
at a time. Before upgrading the speeds on the turn-out beyond 15 km/h
, the track structure of loop lines be strengthened as prescribed. |
| |
BACK |
|
 |
| |
|
| |
INDIAN
RAILWAYS PERMANENT WAY MANUAL |
| |
LIST
OF ADVANCED CORRECTION SLIPS ISSUED SINCE OCTOBER 2001 ISSUE OF THIS
JOURNAL |
| |
The following
correction slip have been issued since the last issue (October 2001)
of the Journal. |
| |
|
| |
| ACS No. |
Para (s) affected |
File No. |
Date of AC slip |
Brief subject. |
| 77 |
248 & 322 |
No.Track/21/93/0503/7 |
12.8.2002 |
Track structure for different categories of track. |
| 77 |
1408 |
No.98/Track-III/TK/17/Vol.II |
9.9.2002 |
Picking up of slacks |
|
| |
|
| |
INDIAN
RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
|
| |
Advance
Correction Slip No. 77 Dated 12.8.2002
(Ref. Railway Board’s letter No. Track/21/93/0503/7 dated 12.08.2002)
|
| |
Sub: Advance
Correction Slip No.77 to the Indian Railways Permanent Way Manual
– 1986. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in the enclosed Advance Correction Slip No.77 dated 12.8.2002,
to relevant para of the IRPWM, be made. |
| |
Receipt of
this letter may please be acknowledged. |
| |
|
| |
The para 248(2)
(a) be replaced with the following : |
| |
|
| |
(a) Broad Gauge
– The following minimum rail sections are recommended based
on the speeds obtainable and the traffic conditions : |
| |
|
| |
| ROUTES |
| Traffic density in GMT |
A |
B |
C |
D. Spl |
D |
E.Spl |
E |
| More than 20 |
60 kg |
60 kg |
60 kg |
60 kg |
60 kg |
60 kg |
60 kg |
| 10-20 |
60 kg |
60 kg |
60 kg |
60 kg |
52/90 |
60kg |
52/90 |
| 5-10 |
60 kg |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
52/90 |
| Under 5 |
52/90 |
52/90 |
52/90 |
52/90 or 60kg (SH) |
52/90 or 60kg (SH) |
52/90 or 60kg (SH) |
52/90 or 60kg (SH) |
| Loop Line |
52 kg IRS T –12 second quality rails or
52 kg (SH) |
| Pvt Sidings |
For sidings with operating speed more than
80 kmph and upto 100 kmph |
Track structure specified for D route. |
| For sidings with operating
speed more than 50 kmph and upto 80 kmph |
Track structure specified for
E route. |
| Where BOX’N or 22.1 tonne
axle wagon ply or operating speeds on sidings exceed 30
and are going upto 50 kmph |
52 kg IRS T-12 second quality
rails or 52 kg (SH) |
| For other sidings with operating
speed upto 30 kmph. |
52 kg IRS –T-12 third
quality rails also called ‘Industrial use rails’
or 52 kg (SH). |
|
|
| |
Note : 52/90
represents 52 kg /90 UTS rail section. |
| |
(i) Existing
90 R rails may be allowed to remain for speeds not exceeding 110 kmph.
|
| |
|
| |
(ii) On routes
identified for running of 22.1 Tonne axle load wagons, 60-kg rails
shall be used on all routes. |
| |
|
| |
(iii) Head
hardened rails should be used on (a) Local lines where dedicated EMU
stock is running. (b) Ghat section with gradients steeper than 1 in
150 and/or curves sharper than 2 degree, (c) Locations where due to
grades, curves, traffic density and type of stock, the rate of wear
of rails is such as to necessitate rail renewal, on wear considerations,
at a frequency of 10 years or so. (d) Routes where predominantly captive
rolling stock is moving in close circuit movement, particularly with
heavy mineral traffic. (e) The Illf rails should be laid on continuous
and long stretches. |
| |
|
| |
(iv) *Second
hand 52 kg rails may be used on case-to-case basis, with the prior
approval of Railway Board, depending upon quality of released rails
available.
The existing para. - 322 of Indian Railways Permanent Way Manual
be replaced to read as under:- |
| |
|
| |
322.
Identification of different qualities or rails in the Field - |
| |
|
| |
(1)
First Quality Rails (T -12) - Indian Railways specification
IRS - T -12/96 gives the detailed specification of Flat Bottom Rails
60 kg. and 52 kg. of grade 880 MFa, 1000 MFa and 1080 MFa. 52 kg./m
and 60 kg./m rails shall be classified as Class' A' and Class 'B'
rails based on tolerance in End Straightness. The rails shall have
rolled on it, the rail section, the Grade of steel, identification
marks of the manufacturer, month and last two digits of the year of
the manufacture, process of steel making and direction of rolling
of rail. |
| |
|
| |
(2)
Second Quality Rails - These are rails with relaxation in sectional
tolerance as provided in Amendment to IRS- T -12/96 but other wise
conforming to T-12/96 in all other respects. The identification of
such rails will be one hole of 6 mm ilia, champhered at both ends,
drilled at the center length of the rail and at the middle of the
web. These rails shall be used only on loop lines/sidings with speed
restriction of 50 kmph. These rails shall be painted with orange colour
on both sides of the web for a distance of 1 metre from each end,
for easy identification. |
| |
|
| |
(3)
Third Quality Rails - In addition to above two qualities, third
quality rails supplied by Steel Plants are arising, particularly during
the inspection of rails while producing first quality rails as per
IRS- T -12 specification. There is no deviation in chemical composition
or mechanical property in 'Industrial Use' rails from that of IRS-T-12.
The deviations exist only in tolerance in surface defects, dimensions
and straightness. These can be used in industrial sidings where speeds
are limited to 30 km p.h in B.G. and 2S km.p.h in M.G. |
| |
|
| |
The identification
of such rails will be one hole of 12m dia., champhered at both ends,
drilled at the center length of the rail and at the middle of the
web. A marking “I.U.” in 18 mm, size shall be stamped
on both end faces of rail. The third quality rail shall be painted
with white paint on end face of the flange and on both sides of flange
for a distance of 500 mm, from each end for identification. |
| |
BACK |
|
 |
| |
|
| |
Advance
Correction Slip No. 78 Dated 9.9.2002
(Ref. Railway Board’s letter No.98/Track-III/TK/17 Vol.II dated
9.9.2002) |
| |
|
| |
Sub: Advance
Correction Slip No.78 to the Indian Railways Permanent Way Manual
– 1986. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in the enclosed Advance Correction Slip No.78 dated 9.9.2002,
to relevant para of the IRPWM, be made. |
| |
Receipt of
this letter may please be acknowledged. |
| |
|
| |
Correction
Slip No.78 dated 9.9.2002 |
| |
|
| |
The para 1408(1)
(c ) of the Advance Correction Slip No.67 dated 24.4.2001 of Indian
Railway Permanent Way Manual – 1986, be substituted as under:
-
1408(1) (c ) – For spot attention / slack picking, multi-purpose
Tampers and Off-track Tampers shall be used as a regular measure
on Concrete Sleepers Track, in the following areas of application:
i) Picking up slacks in isolated stretches.
ii) Points and Crossings areas.
iii) Approaches to bridges and level crossings.
iv) Buffer rail joints /switch expansion joints in LWR section.
v) Block insulated joints /glued joints in track circuited stretches.
For off-track tampers, the working instructins, issued by Railway
Board/RDSO as amended from time to time, should be followed.
As an interim measure, where off-track tampers are not available,
the packing may be done with the help of Crow bar/Beater, duly taking
care that the concrete sleepers are not damaged.
|
| |
BACK |
|
 |
| |
|
| |
INDIAN
RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION) |
| |
Advance
Correction Slip No. 79 Dated 10.10.2002
(Ref. Railway Board’s letter No.97/CE-II/TK/8 dated 10.10.2002) |
| |
|
| |
Sub: Advance
Correction Slip No. 79 to the Indian Railways Permanent Way Manual
- 1986 para-283. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition in
the enclosed Advance Correction Slip No. 79 dated 10.10.2002 in supersession
of Advance Correction Slip No.71 dated 17.7.2001 Para- 283(2) (c)
of IRPWM -1986 be replaced. |
| |
|
| |
Correction
Slip No.79 dated 10.10.2002 |
| |
|
| |
The following
may be replaced in supersession of Advance Correction Slip No.71
dated 17.7.2.002 Para 283 (2) (c) of IRPWM:. 1986 to read as under:-
|
| |
|
| |
(c) "No
part of the tree shall be nearer than 4 mts from the nearest live
conductor. Any tree or branches likely to fall on the live conductor
should be cut or trimmed periodically to maintain the safety clearances.
The responsibility for wholesale cutting of the trees, i.e. cutting
of tree trunks, will rest with the Engineering Department. In the
electrified territories, however, the cutting of the trees shall be
done by the Engineering, Department in the presence of authorized
TrD staff to ensure safety and satisfactory completion of the work.
The day-to-day trimming of the tree branches, wherever required, to
maintain the 4 m safety clearances from OHE shall be done by the authorized
TrD staff and Supervisors.
In case of dispute, the decision whether to cut or trim a tree, shall
be taken through a joint inspection of Engineering and Electrical
officials.
The modalities to be adopted for cutting/trimming of the trees i.e.
contractually or departmentally, may be decided by the respective
departments based on local conditions. Accountal and disposal of trees
cut wholesale will be done by the, Engg. Deptt. while the disposal
of the trimmed tree branches will be the responsibility of the TrD
Department. The expenditure for cutting/trimming of trees to maintain
safe clearance for OHE, shall be debited to revenue grant of' TrD
Department." |
| |
BACK |
|
|
| |
|
| |
Advance
Correction Slip No. 80 Dated 2.12.2002
(Ref. Railway Board’s letter No.98/CE-II/CS/2 dated 2.12.2002) |
| |
|
| |
Sub: Advance
Correction Slip No, 80 to the Indian Railways Permanent Way Manual
- 1986 para-264. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in enclosed Advance Correction Slip No, 80 dated 02.12.2002,
to relevant para of the IRPWM, be made. |
| |
|
| |
Correction
Slip No.80 dated 2.12.2002 |
| |
|
| |
New para may
be inserted as 264 (4) and 264(5) of the IRPWM – 1986 as mentioned
below:
Para 264 (4) – In new line
construction, ballast requirements will be assessed as
per the profile (to be adopted) given in para 263 (I).
Para 264 (5) – The quantities
assessed vide sub-para in (2), (3) and (4) above will be the net
quantities of ballast required, to recoup the deficiencies or to
provide required profile/section. The above net quantities may be
enhanced suitably (say 8%) to arrive at gross quantities of ballast
for the purpose of procurement action in case measurements are proposed
to be taken in stacks or in wagons at originating station.
|
| |
BACK |
|
|
| |
|
| |
Advance
Correction Slip No. 81 Dated 3.12.2002
(Ref. Railway Board’s letter No.2002/CE-II/PRA/7 dated 3.12.2002) |
| |
|
| |
Sub:
Advance Correction Slip No. 81 to the Indian Railways Permanent Way
Manual -1986 para-914. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in the enclosed Advance Correction Slip No. 81 dated 03.12.2002,
to relevant para of the IRPWM, be made. |
| |
|
| |
Correction
Slip No.81 Dated 03.12.2002: |
| |
|
| |
The existing
Para 914 (b) (v) of Indian Railways Permanent Way Manual be modified
to read as under:
(v) - Check rails of level crossings are required to be removed
for tamping" operations, overhauling of level crossings, distressing
of LWR or track renewals etc. Check rails should be refixed as quickly
as possible and preferably before leaving site.
Should a situation arise where check rails cannot be refixed for
any reason and trains have to be passed, a speed restriction of
30 kmph should be imposed besides ensuring that road traffic is
diverted till the check rails are, put in place. In case such diversion
is not possible, temporary arrangements should be made for passage
of road traffic till the check rails are put in place. However,
in both these cases, the check rails should necessarily be provided
latest by close of next day. In such cases, a stationary watchman
shall be posted to ensure safety. |
| |
BACK |
|
|
| |
Advanced Correction Slip No.82 Dated
02..2003:
(Ref. Railway Board’s letter No. 98/CE-II/TK/2 Pt. dated
2.2003)
|
| |
|
| |
Sub:
Advance Correction Slip No. 82 to the Indian Railways Permanent Way
Manual -1986 para–1122(4). |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in the enclosed Advance Correction Slip No. 82 dated .2.2003,
to relevant para of the IRPWM, be made. |
| |
|
|
Correction Slip No.82 Dated 02..2003:
|
| |
|
| |
The existing
para 1122 (4) (iii) of Indian Railways Permanent Way Manual be modified
to read as under: |
| |
|
| |
The rail dolley shall be protected by a flagman at a distance of 1200
metre on Broad Gauge and 800 metre on MG/NG from the rail dolley,
on a double line in the direction from which trains may approach,
and by two flagmen one on either direction on single line. The flagmen
shall also carry three detonators for use in any emergency. |
| |
BACK |
|
|
|
|
| |
Advance
Correction Slip No. 83 Dated 25.02.2003
(Ref. Railway Board’s letter No. 91/Track-III/TM/26 Vol.III
dated 25.2..2003)
|
| |
|
| |
Sub:
Advance Correction Slip No. 83 to the Indian Railways Permanent Way
Manual -1986 para–606. |
| |
|
| |
Ministry of
Railways (Railway Board) have decided that correction/addition as
indicated in the enclosed Advance Correction Slip No. 83 dated 25.2.2003,
to relevant para of the IRPWM, be made. |
| |
|
| |
ADVANCE
CORRECTION SLIP No. 83 Dated 25.2.2003
|
| |
|
| |
The existing
para 606 of Indian Railways Permanent Way Manual be modified to read
as under: |
| |
|
| |
606. Frequency
of Track Recording - Track geometry monitoring of Metre Gauge routes
is not to be done by track recording car. The Broad Gauge routes should
be monitored by TRC as pe |